Only 13 Big Push projects half done by June – Amin Adam asks ‘where has the money gone?’ in budget debate
ACCRA, Nov. 19 – Former Finance Minister Dr Mohammed Amin Adam has told Parliament that only 13 projects under the government’s Big Push infrastructure programme had reached 50 per cent completion by June, and has demanded to know “where the money has gone.”
Dr Amin Adam, the Ranking Member on Parliament’s Finance Committee, made the claims during the debate on the 2027 Budget on Wednesday, November 18, 2026, MyJoyOnline and 3News reported.
“Even with the Big Push that they have made so much noise about, when you look at the scorecard, it doesn’t tell a good story,” he said. “As of June in the mid-year budget, this was the scorecard: only 13 projects of the Big Push had reached at least 50 per cent, and 15 were between 25 per cent and 50 per cent, and a whopping 59 per cent they could not even give account of their status.”
“So where has the money gone?” he asked.
Government’s own scorecard
The figures come from the government’s own reporting. Presenting the mid-year budget review in July, Finance Minister Dr Cassiel Ato Forson said 87 Big Push projects had commenced, with 13 past the halfway mark and six of those beyond 75 per cent, as at the end of June, according to 3News.
The 2027 Budget allocates GH¢29.8 billion to the Big Push next year, close to double the GH¢14.3 billion the government says it spent on the programme in the first ten months of 2026. Within that sum, the Ghana Market Access and Connectivity Project is to receive GH¢2 billion and the Volivo Bridge GH¢400 million to begin construction, 3News reported.
GH¢165m for 24-Hour Economy Secretariat questioned
Dr Amin Adam also questioned the GH¢165 million allocated in the 2027 Budget to the 24-Hour Economy Secretariat, arguing that its programmes have now been moved under the government’s New Economy policy.
“I was hoping that the Finance Minister would admit that the 24hr economy has failed after he moved all policies under the project to the new economy policy, he failed to do that,” he said. “Taking all the programmes from the 24hr economy and putting them under the New Economy, the 24hr secretariat has nothing more to do. The Minister has allocated GH¢165m to the secretariat and I don’t think this is the way we should use our resources.”
He further claimed that spending on goods and services to run government had risen by 67 per cent, from GH¢749 million to GH¢1.2 billion. “The government is spending on itself,” he said, adding that it was “not investing in the productive sectors of the economy.”
Government side defends record
Government speakers defended the programme during the same debate. According to 3News, one said the Roads Minister would publish the list of Big Push projects.
Minister of State Felix Kwakye Ofosu said the 24-Hour Economy was already delivering, pointing to import exemptions for machinery registered with the secretariat. He said 12 oil marketing companies now run 247 outlets round the clock, 13 depots and refineries work continuously, and 12 state enterprises and the DVLA offer 24-hour services.
The Big Push is the government’s flagship roads and infrastructure drive, and its progress is likely to remain a central issue as Parliament continues to debate the 2027 Budget.
Source: MyJoyOnline; 3News.