The Ministry of Energy has named Dansoman, Adenta, parts of Oyarifa, Pokuase, Amasaman and Lakeside among the areas worst hit by recent power outages in Accra, and blamed the problem on pressure on transmission and distribution networks rather than a shortage of generation.
The ministry’s Director of Communications and spokesperson, Richmond Rockson, described the communities as “hotspots” on JoyNews’ Newsfile on Saturday, November 28, MyJoyOnline reported.
“For the generation side, as I mentioned, we’ve largely dealt with the problem. We don’t have any generation issues. But when it comes to the transmission and the distribution, there are serious issues with that,” he said.
Heat, overloaded lines
Mr Rockson said years of under-investment in transmission had left some lines overloaded, causing low voltages in some communities, while the current hot weather had pushed up demand. “In the last four to eight weeks, we all know that it’s very hot. The El Niño, as we are experiencing, and anybody could tell you that the weather has an impact on the energy systems,” he said.
He said about 2,000 transformers had been deployed across the country this year, and that capacity on the K1 and K2 transmission lines in Kumasi was being tripled. “Let me assure the people of Ghana that we are responding swiftly to the issues,” he said.
Funding delays defended
Mr Rockson also defended delays in approving funding for some energy-sector programmes, after a June 2026 World Bank report – cited by MyJoyOnline – downgraded Ghana’s Energy Sector Recovery Programme to “unsatisfactory”, partly over delays in financial authorisations. He said the Finance Ministry was auditing programmes because some facilities had been spent on items such as vehicles rather than their main purpose.
“Because some of these facilities are World Bank facilities and you pay for it, they are not free monies,” he said. “If you’re going to be downgraded because you want value for money, I’m sure that you prefer that than you spending the money and not getting value for it.” He said the government had engaged the World Bank and expected progress to show at its next assessment.
Analyst: transmission neglected
On the same programme, Kwadwo Poku, Executive Director of the Institute of Energy Policies and Research, said the outages showed transmission had been neglected. “In 2020, I made a statement that the next erratic power disruption in this country will be transmission, not generation,” he said.
Mr Poku said a US$50 million component of a US$250 million World Bank facility meant for GRIDCo transmission work, including the Takoradi–Kasoa 161kV line, was held up partly because the Finance Ministry had not given commitment authorisation, citing a World Bank document. He warned that the problems could persist for some time because transmission investments cannot be completed quickly.
Energy Minister John Jinapor has also insisted that the country is not shedding load, blaming recent cuts on El Niño heat and a gas infrastructure fault.
Sources: MyJoyOnline/JoyNews Newsfile (28 Nov): hotspots; transmission and distribution; funding delays; Kwadwo Poku; GRIDCo funding.
Featured image: Power lines and skyline seen from North Dzorwulu, Accra (file photo, June 2026) – Photo: Efo Komla via Wikimedia Commons (CC BY-SA 4.0).